Construction Update

Progress is continually moving along with majority of the focus on raising the second island of the Artist Village, filling on the oceanfront lots and completion of Isla San Jose.  The filling of the Artist Village is advancing and will be completed in 10 days.  At that time construction will then proceed immediately with levels, marking lots and forming streets.  On Isla San Jose installation of utilities has begun which include sanitary drainage, network facilities (land lines, cell phones, data transmission and television), potable water and electric.  Construction for bridge accesss to the island has also begun.  We have advanced on street construction of Baja Boulevard which allows access to the new beach club area.  Finally, we have begun construction in the quarry to harvest Laja stone for the paving of roads.  We will begin first on Isla San Jose and currently have 30% of the required material.